Rescuers recover more bodies from the rubble of the six-storey structure in Admin Society, while police investigate alleged illegal construction and courts examine the case.
KARACHI, November 28, 2026: The death toll from the collapse of an under-construction six-storey building in Karachi’s Administration Employees Housing Society (Admin Society) has risen to 11 after rescue teams recovered more bodies from the rubble on Saturday.
The building collapsed near Baloch Colony on November 25, trapping construction workers beneath concrete and debris. Four people were initially reported dead, while 14 injured individuals were rescued on the day of the incident.
Rescue officials said the search operation was continuing, with teams using specialised equipment and carefully clearing the wreckage. A marble worker was rescued alive on Friday, nearly two days after the collapse. Of the 14 injured people, 13 have reportedly been discharged from hospital, while one remains under treatment.
Rescue 1122 teams have created pockets in the debris to reach areas where people may still be trapped. Operations are being conducted cautiously because heavy machinery could damage bodies beneath the rubble or destabilise the remaining structure.
Illegal construction under investigation
Initial findings indicated that approval had been granted for a building comprising a basement, ground floor and one additional storey. However, six extra floors were allegedly constructed in violation of the approved plan.
Police registered a case involving charges related to murder, negligence and carelessness. Ten people were nominated, and four suspects — Yar Muhammad, Afzal Khan, Munir Akram and Saad Tahir — were remanded in police custody for five days by a judicial magistrate.
During the hearing, the investigating officer told the court that the building’s approved plan allowed only ground-plus-one-storey construction. The defence questioned the arrests, arguing that some suspects were workers or relatives of the contractor rather than the building’s owners.
The court questioned why the building owner, contractor and relevant Sindh Building Control Authority (SBCA) officials had not been arrested. It directed the investigating officer to submit a progress report.
Court vacates interim stay order
Separately, a civil court vacated an interim stay order concerning the collapsed building after the plaintiff failed to present arguments on an application for an interim injunction despite several opportunities.
The Senior Civil Judge (South) was hearing a suit filed by the building owner against the SBCA. The court also issued notices on the authority’s application seeking dismissal of the suit and directed replies by December 4.
Sindh government takes action against officials
Sindh Chief Minister Murad Ali Shah ordered action against officials over alleged negligence. The government removed Waseem Shamshad from the posts of SBCA Director General and Local Government Secretary and ordered the suspension of 16 SBCA officers.
Deputy Commissioner East Nasrullah Abbasi and SSP East Zubair Sheikh were also ordered to be removed. The chief minister directed police to arrest the building owner, Salman Tahir, and builder Zeeshan, while instructing investigators to examine the roles of the architect and structural engineer.
The incident has renewed concerns about unauthorised construction and weak enforcement of building regulations in Karachi, where building collapses have previously caused significant loss of life.